The outcome is rather unsurprising but, even so, the Court of Appeal’s judgment in URS Corporation Ltd v BDW Trading Ltd [2023] EWCA Civ 772 provides some useful guidance on:
In summary the Court of Appeal held that:
Housing developer BDW Trading (“BDW”) engaged a construction engineering firm, URS Corporation (“URS”), to design homes for two developments in London and Leicester, respectively. Building works for the London development were completed in or around March 2007 to February 2008, while the Leicester development was completed between February 2005 and October 2012. BDW sold both developments after practical completion and transferred its interests in them by December 2008 and May 2015, respectively.
Following the Grenfell Tower disaster in 2017, BDW conducted a review which identified structural design defects in respect of the London and Leicester developments. BDW subsequently incurred significant costs investigating the defects and carrying out mitigation, including evacuating one apartment block in the London development, and undertaking permanent remedial works.
The underlying dispute concerns URS’ liability to BDW for the losses BDW had incurred in investigating and remediating the design defects in the developments. However, the Court of Appeal’s decision is concerned with a number of Appeals by URS as to whether BDW was entitled to amend its claims against URS to add claims under the DPA and CL(C)A in light of the new limitation provisions under the BSA. Permission for such amendments had been granted by the High Court.
There were three Appeals:
The first appeal was in relation to the decision of a preliminary issue regarding BDW’s claim against URS in negligence (which was dismissed).
The Grounds, broadly, were that:
The Court of Appeal dismissed all Grounds. Of particular interest is that:
As to (1), the Court of Appeal found that the specific wording of s.135 of the BSA, namely, “is to be treated as always having been in force”, was clear that it was intended to have retrospective effect and there was no carve-out for ongoing proceedings.
As to (2) the Court found it was clear on the words of s.1(1)(a) that the dwellings were “provided to the order of” BDW (as developer) and so BDW was owed the DPA s.1(1) duty by URS. Additional submissions by URS that:
As to (3), the Court of Appeal found that recoverability of damages under the DPA is not linked to, or limited by, property ownership.
As to (4), the Court of Appeal found that as a matter of statutory construction there was nothing in the wording of s.1(1) of the CL(C)A to suggest that the making or intimation of a claim was a condition precedent to the bringing of a claim in contribution. The Court of Appeal also considered the fact that while the need to make a claim is expressly referred to in s.1(4) CL(C)A, there is no similar requirement in s.1(1), which suggests it was never intended to be a condition precedent to bringing a claim in contribution.
The Court also noted that s.1(6) CL(C)A refers to “any such liability which has been or could be established” which strongly suggests that the potential liability of party B (in this case BDW) does not need to be established in fact before the right to claim a contribution against party C (in this case URS) arises. The Court also considered that there was no reason why BDW should have to wait for a claim from party A, for example the homeowners, before being entitled to seek contribution from URS as that would reward laziness.