1 Forest were to pay Able £150,000 in four instalments, in addition to the adjudicator's fee which was due immediately.
2 It was in full and final settlement of all claims or liabilities in relation to the work, provided Forest paid in full.
3 In the event that Forest failed to pay an instalment, Able could enforce the adjudicator's decision with full costs and interests.
Forest paid the first instalment, however defaulted on the second, and consequently Able commenced proceedings on 7 January 2009 pursuant to CPR Part 8 in the TCC for the sum of £110,000 outstanding under the Agreement. The parties then met on site on 15 January 2009, and Forest gave Able with a cheque for £10,000 which was honoured. Further to this, Forest alleged that another settlement agreement was made, varying the terms so that the debt would be paid off at a rate of £3,000 a month. Able denied this, stating that this would simply not have been agreed to due to the fact that it was already in debt and this arrangement would take almost three years for the full sum to be paid off.
Forest did not attend the enforcement hearing, and neither party could afford the solicitors that had instructed them in the original adjudication. The first issue that arose was whether the Agreement affected the enforcement claim. On occasions, a settlement or compromise agreement may not be a construction contract within the meaning of the HGCRA. However, in this situation, the adjudicator had not been appointed under the settlement agreement itself, and Mr Justice Coulson found the Agreement to be of limited relevance. It merely dictated what should occur should Forest default. The Court should not adopt a different approach
The Judge also had to consider, in Forest's absence and without their oral evidence, if another settlement agreement had been reached on 15 January 2009. He decided that the court procedures ought to be flexible enough to ensure that a point such as this should be addressed straightaway in order to prevent parties from avoiding summary judgment by raising an issue which required oral evidence. Thus, the Judge heard the evidence from Able and held that Forest were indeed in breach of the existing Agreement. Therefore, Able were entitled to judgment for the unpaid balance of £100,000 pursuant to the original adjudicator's decision.