Was Azimut entitled to summary judgment under the guarantee? Was the liquidated damages clause a penalty and so unenforceable?
Contract issues
13 August 2010 - City Inn Ltd v Shepherd Construction Ltd
What is the correct approach to be taken when awarding extensions of time for concurrent delay?
6 August 2010 - Geldof Metaalconstructie NV v Simon Carves Ltd
Was SCL entitled to set off its counterclaim for repudiation of the Installation Contract, either contractually or under the Court’s equitable jurisdiction, against amounts claimed by Geldof under the Supply Contract?
3 August 2010 - Traditional Structures Ltd v H W Construction Ltd
Was there a mistake about the contract sum figure? If so, could anything be done about it?
2 July 2010 - WW Gear Construction Ltd v McGhee Group Ltd
Was the clause which set out how McGhee should proceed when making a claim for loss and/or expense a condition precedent?