Recent Cases
For the past couple of years, we have been
responsible for the editorship of CILL; and many of case
summaries that appear below are extracted from the CILL
reports. CILL is published 10 times a year; if you are
interested in subscribing, contact Alison Levers at Legal
Studies Publishing Ltd on 0171 453 2274.
The following cases are noted below; an index
appears at the end of this Review
Abbey National Mortgages v Key Surveyors
AEG v Translift Monorail
Alfred McAlpine Homes v Property
and Land
Balfour Beatty v Docklands Light
Railway
Birse Construction v Haiste
B Mullan v Ross
Bristol & West Building Society
v Christie
Bowmer and Kirkland v Wilson Bowden
Clarksteel v Birse Construction
Colt International v Tarmac Construction
John Barker v London Portland Hotel
Havant BC v South Coast Shipping
Hoppe v Titman
Vascroft v Seeboard
Birse Construction
Limited v Haiste Limited and Others
Court of Appeal Sir John May and Roach and
Nourse LJJ (Judgment delivered 5th December
1995)
This case was managed on behalf of the Engineer
by Simon Tolson.
Facts
Anglian Water Authority (‘Anglian’) employed
Birse to build a reservoir pursuant to a Design and Build
Contract. The Engineer named in the Contract was an employee
of Anglian, Mr. Newton. Birse engaged Haiste as subcontract
designers.
The reservoir leaked. Birse agreed with
Anglian to build a new reservoir, and sued Haiste for
damages.
Haiste sought a contribution from Mr. Newton.
At first instance, His Honour Judge Cyril Newman held (CILL
page 1034) that Mr. Newton’s potential liability to Anglian
could be a liability in respect of ‘the same damage’ as the
liability of Haiste to Birse, within the meaning of the Civil
Liability (Contribution) Act 1978.
Mr Newton appealed.
THE STATUTORY PROVISION
Section 1(1) of the 1978 Act provides as
follows:-
‘Subject to the following provisions of this
Section, any person liable in respect of any damage suffered
by another person may recover contribution from any other
person liable in respect of the same damage (whether jointly
with him or otherwise).’
THE ARGUMENTS
Before the Court of Appeal, Haiste ran two
lines of argument.
Its primary line of argument was that taken
by the Official Referee at first instance, namely that there
are no express words in the Act requiring that the person from
whom contribution is sought is liable to the same person as he
who seeks the contribution; it is sufficient if the person
from whom the contribution is sought is liable to someone
else.
Haiste’s alternative argument, not raised in
the Notice of Appeal, involved the 1978 Act being applied
twice. First, it was said that, if Anglian had sued Birse
instead of coming to the agreement for the rebuilding of the
reservoir, then Birse could have issued contribution
proceedings against Mr. Newton under the 1978 Act, such that
Newton should be regarded as liable to Birse. Applying the Act
a second time, it was said that Haiste could therefore recover
a contribution from Newton, in that both Haiste and Newton
were liable to Birse.
On behalf of Mr Newton, it was argued that,
on a proper construction of the Act, the liability of a person
from whom contribution is sought must be to the same person as
the person to whom the person seeking contribution is liable.
Further, it was argued that Mr. Newton could not be liable for
‘the same damage’ as Haiste, because the damage suffered by
Anglian (disruption while the new reservoir was being built)
was different from the damage suffered by Haiste (the cost of
building the replacement reservoir).
Issues and findings
Can a claim for contribution under the 1978
Act be founded on liability to a stranger to the action?
(Reversing the first instance decision)
No.
Was the damage suffered by Anglian the same
as the damage suffered by Birse?
(Reversing the first instance decision)
No.
Commentary
Had the first instance decision in this case
not been overruled, it would have potentially opened the way
for a plethora of unusual claims. The Court of Appeal judgment
restores the position to what was previously believed to be
the effect of the 1978 Act, namely that it is a mechanism
whereby a liability could be spread out amongst various people
liable to the same Plaintiff, even if that Plaintiff did not
sue them all himself.
Vascroft (Contractors)
Ltd v Seeboard plc
Official Referee's Business His Honour
Judge Humphrey Lloyd QC (Judgement delivered 10th January
1996)
Facts
Vascroft were main contractors for
construction of three buildings in Mayfair. They entered into
a subcontract with Seeboard's predecessors, Nene, for
electrical works; the subcontract was based upon the standard
form DOM/2.
The subcontractor had failed to give any
notice to the main contractor that the sub- contract works had
been practically completed.
Disputes arose under the subcontract, which
were referred to the arbitration of Mr Harold Crowter. Mr
Crowter determined certain preliminary points of law, from
which Vascroft wished to appeal.
Issues and findings
Is the standard form of "preconsent" in DOM/2
an effective consent to appeal under the Arbitration Act
1979?
Yes.
Where a subcontractor under DOM/2 fails to
give notice to the main contractor as to practical completion,
is practical completion of the subcontract works to be
treated as a matter of fact, or is it deemed to be the date of
completion of the main contract works?
It is deemed to be the date of completion of
the main contract works.
Why?
Because a subcontractor who fails to give
the required notice of practical completion should not be in
any better position than he would have been in if he had given
the notice and the main contractor had dissented from it.
STATUTORY PROVISION
Section 1(3) of the Arbitration Act 1979
(Appeals to the High Court on any question of law arising out
of any Arbitration award) provides as follows:-
An appeal under this section may be brought
by any of the parties to the reference -
- with the consent of all the other parties to the
reference; or
- subject to section 3 below, with the leave of the
court.
DOM/2 PROVISIONS
"14.1 The subcontractor will notify the
Contractor in writing of the date when in his opinion the
subcontract Works are practically completed and if not
dissented from in writing by the Contractor within fourteen
days of receipt of the subcontractor's written notice
practical completion for all the purposes of the subcontract
shall be deemed to have taken place on the date so notified.
Any written notice of dissent shall set out the Contractor's
reasons for such dissent.
14.2 When the Contractor gives written notice
of dissent under clause 14.1 practical completion for all the
purposes of this subcontract will be deemed to have taken
place on such date as may be agreed. Failing such agreement
practical completion will be deemed to have taken place on the
date of Practical Completion of the Works set out in the
statement of the Employer issued under clause 16.1 of the Main
Contract Conditions."
"The parties hereby agree and consent
pursuant to sections 1(3)(a) and 2(1)(b) of the Arbitration
Act 1979 that either party
…may appeal to the High Court on any
question of law arising out of an award made in an
arbitration under this Arbitration Agreement ...
"
Commentary
The decision of the Court as to the
effectiveness of the JCT mechanism for "preconsent" to appeal
from arbitrators awards is hardly surprising; the decision is
however useful as settling a matter which has been the subject
of some speculation.
Nor is it surprising that clause 14 of DOM/2
has ended up before the Courts, for it heaps obscurity upon
absurdity. The apparent intention of Clause 14 is that the
subcontractor should give notice as to when he regards his
subcontract works as practically complete, but all the main
contractor has to do is to disagree with that notice;
practical completion of the subcontract works is then deemed
not to take place until completion of the main contract works.
Provisions such as this are not only absurd in their effect,
but encourage the playing of contractual games, and hence
disputes.
The clause also illustrates a point all too
often forgotten by contract draughtsmen: that the more
procedural requirements are put into a contract, the more
certain it is that procedural anomalies will occur. In this
case, the procedure left the contractual tracks at a very
early stage, such that on the express wording of the contract
the deeming provision did not bite. The general proposition of
law that "no man may take advantage of his own wrong" is of
general application, but it is somewhat surprising that the
Court invoked it in order to plug the gap in such an
apparently unreasonable clause.
Alfred McAlpine
Homes North Ltd v Property and Land Contractors Ltd
Official Referee's Business His Honour
Judge Humphrey Lloyd QC (Judgment delivered 31st July
1995)
Facts
Alfred McAlpine Homes North Limited
("McAlpine") engaged Property and Land Contractors Ltd ("PLC")
under a JCT80 Contract to build 22 houses at Shipton. McAlpine
gave PLC an instruction to postpone the works, pursuant to
which PLC submitted a claim for loss and expense under Clause
26 of the contract. The claim was disputed, and referred to
the arbitration of Mr Keith J Rawson. In a first interim
award, Mr Rawson found that PLC was not entitled to recover
loss of overhead profits on the Emden Formula, but was
entitled to recover on the basis of overhead actually expended
and not recovered during the period of delay. In his second
interim award, Mr Rawson awarded PLC the sum of £59,661.68 as
additional head office overheads incurred and not recovered
elsewhere; he further awarded PLC £3,717.70 in respect of
small plant which PLC owned, but for which PLC claimed on a
notional hire rate basis.
McAlpine appealed.
Issues and findings
Was PLC entitled to its award in respect of
overheads and profit?
Yes. The Court discussed this issue
generally.
Where a contractor owns a small plant, is he
entitled to quantify his loss and expense claim on the basis
of notional hire rates?
No. The claim must be advanced on the basis
of actual loss.
Commentary
Given the huge amount of commentary on the
Hudson/Eichleay/Emden Formulae, and the wealth of United
States authority on the topic, there are remarkably few
English decisions on the applicability of these formulae. The
Hudson Formula obtained judicial approval in general terms in
J F Finnegan Limited v Sheffield City Council (1988) 43 BLR
124.
The facts of this case were somewhat unusual,
in that PLC asserted that its policy was to carry out only one
contract at a time, and the arbitrators findings were not
entirely clear as to the extent to which this was found as a
fact. This judgment is accordingly of more interest for its
general review of the subject than for its application on the
particular facts.
In general terms, the approach of the Court
seems to have been to support the general view that the
formulae are appropriate in some circumstances, but the
formulae do not relieve the contractor of the need to show
that he has suffered at least some loss in terms of overheads
and profit by reason of a delay.
The decision on small plant is also welcome,
notwithstanding that the sum involved in this case was modest.
It is very common for contractors and subcontractors to
include sums in loss and expense claims in respect of plant,
and to claim hire rates regardless of whether the plant was
hired or owned. This judgment firmly establishes that such
claims are not permissible where the contractor owns the
plant, and thus has not incurred the hire charge.
Clarksteel Limited v
Birse Construction Limited
Official Referee's Business His Honour
Judge Humphrey Lloyd QC Judgment delivered 20 February
1996
Facts
The Plaintiffs were welding subcontractors
to the Defendants in relation to steel and ductile iron pipe
laying works for a new water mains near Grimsby. The pipes
were supplied as free issue materials by the employer to the
main contractor; the subcontract was in the standard FCEC
"Blue" form of subcontract (revised September 1984). Among
the documents forming part of the subcontract was document 7,
being a Schedule of extra-over rates. It stated:
"Where the weld to an external pipe joint
exceeds the requirement of BS 534 and 3601 for steel pipes,
the following extra-over rates shall apply:-
Steel Pipe Diameter |
Extra-Over Rate |
1000 |
£4.40 |
900 |
£3.40 |
800 |
£2.60 |
Clarksteel complained that the gaps that they
were required to weld were excessive. They issued proceedings,
and various preliminary issues were ordered.
Issues and findings
Was the effect of the relevant British
Standards a matter for expert opinion?
No, although in this case expert evidence was
received "de bene esse".
Assuming that the main Contractor was in
breach of contract in providing pipes which did not comply
with BS 3601, was the subcontractor entitled to damages, or
to a quantum meruit?
Neither. The express agreement as to
extra-over rates was to be treated like a liquidated damages
clause.
Commentary
It is very common for Plaintiffs, in loss and
expense claims, to plead alternative claims in quantum meruit
and/or damages, and the standard wording in JCT contracts to
the effect that the loss and expense provisions are without
prejudice to common law remedies have often been regarded as
"for the avoidance of doubt". This case, however, breaks a
little new ground extending the notion of liquidated damages
clauses to "extra-over" provisions. Previously, it has been
recognised that "Brown" clauses (where the parties pre-agree a
weekly rate for the contractor in the event of prolongation)
have this effect, but this case goes somewhat further.
As a side issue, this case follows the
current trend in limiting the scope for expert evidence.
AEG (UK) Limited v Translift
Monorail Limited
Official Referee's Business His Honour
Judge Bowsher QC Judgment delivered 22nd February 1996
Facts
The Plaintiffs were subcontractors,
providing parts, supplies and amplifiers for use in a thrill
ride in Efteling Park, Holland. The Defendants were main
contractors.
The Plaintiffs claimed the unpaid price of
the equipment; the Defendants counter-claimed, inter alia, for
unfitness for purpose.
The amplifiers provided by the Plaintiff were
manufactured by the Plaintiff's parent, AEG Germany. The
amplifiers were fitted with protection devices, known as
I2t, which were activated by a potentiometer. The
potentiometer was set by the Plaintiff's parent supplier at 6
volts. At that setting, the warning lights came on during
testing on the steepest uphill section of the ride. It
appears, although the evidence was incomplete, that if the
potentiometers had been set to a higher voltage, the equipment
would have passed the tests.
Issues and findings
Is fitness for purpose to be judged in
absolute terms, or within the limits of the manufacturers
instructions?
Within the limits of the manufacturers
instructions.
What is the proper approach to
commissioning?
The purpose of commissioning is to make
adjustments, not to remedy defects.
Commentary
This raises an interesting point about
tolerances. It is very common for suppliers to set "red lines"
substantially below the true maximum performance of their
products. What is the position where a product is physically
capable of performing the required purpose, but only by, so to
speak, swapping the fuse for one of higher rating than
recommended by the manufacturer?
The answer in this case is that the article
is not fit for its intended purpose, although the result may
have been influenced by the consideration that theme park
rides are perceived as inherently dangerous things.
Bristol & West
Building Society v Christie and Others
Official Referee's Business His Honour
Judge Esyr Lewis QC Judgment delivered 15 February 1996
Facts
The Plaintiff Building Society sued both
solicitors (acting for it and the borrower) and valuers in
respect of a loan of £168,683, with the aid of which the
lender, a Mr. Demetrakis, bought Basement Flat, 4 Peto Place,
London, NW1 for £168,000.
The Solicitors settled the claim, paying the
Building Society £170,000 plus costs. The Building Society
assigned its claim against the valuers to the Solicitors, who
brought a claim against the valuers pursuant to the Civil
Liability (Contribution) Act 1978.
Issues and findings
Was the Solicitors' expert sufficiently
qualified to give expert evidence?
Yes; there is no inherent difference in
principle in the process of valuing property whether for
mortgage, tax or sale purposes.
Was it relevant to the question of the
valuer's negligence that the valuation falsely stated that the
signatory had inspected the property?
No.
Is a material error in a valuation prima
facie evidence of negligence?
Yes. Although a party charged with negligence
may in some cases show that reasonable care had been taken in
reaching a wrong conclusion, this was not the case here.
Should the starting point for contribution be
the agreed settlement figure, or what the Building Society
would have obtained in the action but for settlement?
It was conceded to be what the Building
Society would have recovered. The Court proceeded on that
basis.
Could the valuers reduce their contribution
by showing that the Building Society had been contributorily
negligent?
Yes.
Was the sum recoverable by the Building
Society under an insurance policy to be taken into
account?
No.
Was it relevant that the premium for the
Insurance Policy was paid by the borrower?
No.
Given that the Building Society would not
have made the advance if the Solicitors had been
non-negligent, or if the valuers had been non-negligent, how
should the contribution be assessed?
50/50.
Commentary
The resurgence of liability in Tort in
construction cases means that there are likely to be many more
Contributory Negligence cases, and this case required the
Court to consider a number of the issues arising.
Where a Plaintiff sues more than one
Defendant in negligence, it is obviously open to the Court at
trial to apportion liability. Very often, as here, one or more
Defendants wants to settle. If he does settle, he may want, as
here, to recover a part of the settlement money from a
non-settling Defendant. In such circumstances, it is usual for
the settling Defendant to ask for and get an assignment of the
Plaintiffs cause of action against that other Defendant. The
general rule is that it is not possible to assign a bare cause
of action unless there is a sufficient collateral commercial
purpose; but it does now seem to be the settled practice to
regard assignments of causes of action in these circumstances
as proper and valid. No challenge to the validity of the
assignment was made in this case.
Conversely, if the settlement of the settling
party is inadequate, the Plaintiff may continue against other
Defendants, and those other Defendants may join the settling
party back into the action under the 1978 Act. For this
reason, it is common for settling parties in both
circumstances to ask the Plaintiff to indemnify them against
such contribution proceedings; sometimes those indemnities are
forthcoming and sometimes they are not.
Where, as here, the main action is brought
to an end by the settlement, the usual approach is to
seek a contribution in respect of the settlement figure,
rather than the figure which might have been awarded
but for the settlement. That appears to be the intention
of the 1978 Act, which refers in Section 1(2) to the
"payment in respect of which the contribution is sought".
Indeed, it is well settled law that sums paid under
a reasonable and bona fide compromise in settlement
of a legal claim are recoverable, without the person
seeking contribution having to show that he would have
lost the original action. That, for example, was the
conclusion reached by the Court of Appeal in Comyn
Ching v Oriental Tube (1979) 17 BLR 47, applying
Biggin v Permanite [1951] 2KB 314. Attention
thus usually focuses, not upon what the Plaintiff would
have recovered in the original action, but whether this
settlement was reasonable or not. That debate was at
the centre of the cases concerning the relevance of
legal advice reported in CILL in May 1994: Lloyds
v Kitsons (page 940) and DSL v Unisys
(page 942).
It is thus somewhat surprising that it was
apparently conceded in this case that the contribution should
be assessed, not on the settlement figure, but upon what the
Building Society would have recovered had the matter not
settled. The Court proceed on the basis of that concession
without referring to any of the cases mentioned above, but
also without any finding as to whether the concession had been
rightly made.
That route led the Court to consider
the question of whether damages should be reduced by
virtue of the fact that the Building Society recovered
part of the loss from Insurers, the premium having been
charged to the borrower. The Court found that they should
not be so reduced, and it might be regarded as trite
law that insurance recoveries are to be disregarded,
but for an interesting point about payment of the premiums.
In Parry v Cleaver, the House of Lords said
that the real reason why insurance money is disregarded
is that it was "unjust and unreasonable to hold that
the money to which he prudently spent on premiums and
the benefit from it should inure to the benefit of the
tortfeasor". So is there to be a departure from this
principle in cases where the Plaintiff has not himself
borne the cost of the premium? It seems not, and the
only safe way for a party who is paying or contributing
to an insurance premium for a policy not in his name
is to have his interest noted on the policy. In this
respect, the case follows the same policy as National
Trust v Hayden Young (CILL October 1994, page 976)
where a subcontractor was held liable for the cost
of a fire, notwithstanding that, under the terms of
the Contract, the employer agreed to insure against
that risk.
A final point of interest in the case
concerns the way that the Court approached apportionment. On
behalf of the valuers it could be said that the solicitors
caused all of the loss, in the sense that had they done their
job properly, the Building Society would not have advanced the
loan. Conversely, the solicitors could say that it was all the
valuers fault, in the sense that if they had not made a
negligent valuation, the Building Society would not have made
the loan. The Court decided in these circumstances that the
appropriate contribution was 50% (save only for a small
adjustment in respect of a garage issue, which was entirely
the solicitors fault) thereby, perhaps, reflecting the old
maxim that "equity is equality". It certainly follows the
modern trend that when the Courts are assessing contribution,
they tend to adopt a very broad brush approach.
Balfour Beatty v
Docklands Light Railway Limited
Court of Appeal Sir Thomas Bingham MR,
Millet LJ, Pill LJ Judgement delivered 3rd April 1996
Facts
Balfour Beatty was engaged by Docklands Light
Railway for extensive civil engineering works; the contract
sum was approximately £21.8 million.
The contract was based on ICE 5th Edition but
with two significant differences. First, the Employer's
Representative took the place of the Engineer in the Standard
Conditions. Secondly, Clause 66 of the Standard Conditions
(dealing with the settlement of disputes and making provision
for recourse to arbitration) was omitted altogether.
Disputes arose; the contractor sought payment
of some £1.8 million prolongation costs and £1.5 million
construction costs over and above what the Employer was
prepared to certify.
The following preliminary questions were
determined at first instance by Judge Cyril Newman QC:-
- Does the Court have a general power to open up, review
and revise the decisions, opinions, directions, certificates
or valuations of the Employer, in particular:-
- the final determination and certificate of the
Employer under Clause 44.4;
- the final certificate of the Employer under Clause
60.5?
- If not, are the powers of the Court limited to settled
circumstances established in law as justifying interference
by the Courts?
Judge Newman QC answered the questions as
follows:-
- No
- Yes, in particular (where) such decision, opinions,
instructions, directions, Certificates or valuations have
been proved to be not in accordance with the provisions of
the Contract.
Balfour Beatty appealed.
Issues and findings
Does the Court have a general power to open
up, review etc. decisions etc. of the Employer?
No
Are Certificates in these circumstances
merely administrative?
No.
Was the Employer bound to act honestly,
fairly and reasonable, even though there was no such
obligation expressed in the contract?
Yes.
Is the Contractor entitled to a remedy if he
can show breach of such a duty?
Yes.
Commentary
In most standard forms of main contract, certificates
are issued by a professional. Although that person is
usually the agent of the employer, it is well settled
law that he is under a duty to certify fairly as between
the employer and the contractor. The contracts typically
contain arbitration clauses, whereby the arbitrator
is expressly empowered to open up and review certificates.
In NRHA v Crouch (1984) it was decided that
the effect of such a provision was to confer a dual
function upon an arbitrator; he not only has the usual
arbitral function of ruling on what the parties’ rights
are, but under the review provision, he has the power
to alter the rights of the parties. This latter power
is not available to the court save in exceptional circumstances.
In Pacific v Baxter (1988), it was decided
that in these circumstances an aggrieved contractor
does not have the alternative option available of holding
the certifier liable for negligent certification, but
must look to the arbitrator’s powers of review.
It is not uncommon for contracting parties to
amend the standard forms by omitting the arbitration
provisions. Where this is done, it is usual and appropriate
for the contractor to insist on a "de-crouching" clause, so as
to give to the court the power to open up and review
certificates.
Sometimes, the certifier is not a
professional person or firm, but the employer himself. The key
issue here is not whether the certifier is a professional
person or not, nor whether he is an outside consultant or an
"in house" employee, but whether the certifier is the same
legal person as the employer.
Both of these features were present in this
case (ie there was no arbitration clause, and the certifier
was the employer), thereby giving rise to an interesting
conundrum. On the one hand, Crouch says that there is no
general power for a court to open up and review certificates.
On the other hand, it would be a startling and unwelcome
conclusion that the employer had the unfettered right to be
judge and jury in its own cause.
Recognising this difficulty, the employer
here conceded what amounted to an implied term that where the
employer himself is issuing certificates that are not subject
to review, then the employer is bound to certify honestly,
fairly and reasonably.
The court adopted that approach in resolving
the conundrum, but it is not entirely clear how far the
principle applies. Take, for example, the case of
subcontracts such as DOM/1, where the subcontractor is paid
by reference to the main contractor’s valuation; is the main
contractor under a duty to act fairly and reasonably?
Presumably so. How far does a challenge have to go? Is it
sufficient for a dissatisfied party to show unreasonableness?
Is the test subjective, turning upon the certifier's state of
mind, or is it sufficient to show that the certified sum is
unreasonably low? The terms of the judgement in this case
suggests that there is a subjective element, but in practice
it is difficult to see how the court is sensibly going to be
able to approach such cases on the basis of the certifier’s
state of mind, or how damages could be assessed on such an
approach.
What conclusion, then, can be drawn from this
decision? Probably this: that wherever the level of payment
under a building contract is fixed by a non-reviewable
certificate or valuation of one of the parties, then that
party is under an implied duty to act honestly, fairly and
reasonably in relation to such certificates or valuations. The
other party can challenge any certificate or valuation on the
ground that no fair and reasonable person would have issued
the certificate or valuation in that amount, and recover
damages, being such further sum as a fair and reasonable
person would have certified or valued.
If this interpretation be right, then the
decision may be of significant benefit to subcontractors, who
often have reason to complain about the fairness and
reasonableness of the main contractors’ valuations of their
work.
Arguably, the case goes further than that,
and imposes an implied duty of good faith on the employer in
cases where the certifier is not the same person as the
employer. But what then is the mechanism? It has been long
established that where the certifier acts dishonestly, then he
will be disqualified from further acting, but is the employer
under a duty to replace the certifier where the certifier acts
unreasonably? And is the employer vicariously liable in
damages if the certifier certifies unreasonably? These are
questions that are not answered by this decision.
Colt International v Tarmac
Construction Limited
High Court of Justice Mr Justice
Morrison Judgment delivered 4th March 1996
Facts
Tarmac were pursuing arbitration proceedings
against Colt; Mr Christopher Dancaster, a Chartered Surveyor,
was appointed as arbitrator by the RICS.
A dispute arose in the arbitration as to
whether Tarmac had complied with the arbitrator's discovery
order. The arbitrator indicated that, if Colt persisted with
their discovery application against Tarmac, which involved the
question of waiver of privilege, he would wish to take advice
from Queen’s Counsel.
Colt suggested that the discovery application
merited the appointment of a legal assessor to sit with the
arbitrator; the arbitrator gave an indication that he doubted
whether it was necessary to have a QC sitting with him, and
that if Colt insisted then the costs would have to be borne by
Colt in any event. Colt complained that the arbitrator had
pre-judged that issue, whereupon the Arbitrator indicated that
he would review the position in the light of submissions made
to him at the forthcoming hearing.
In the event, the Arbitrator embarked upon
the application without a QC sitting with him, but it became
apparent that he did need legal advice upon the submissions
made to him. Colt complained that the terms upon which the
Arbitrator sought that advice were too wide, and applied for
his removal for misconduct.
Issues and findings
What was the test to be applied on an
application for removal for misconduct?
Whether the circumstances are such that a
reasonable man would think that there was a real likelihood
(in the sense of a real possibility or real danger) of bias.
Should the arbitrator be removed in this
case?
No. The application was groundless, and
should not have been made.
Is a lay arbitrator entitled to assistance
from the parties’ solicitors and counsel in formulating a
question which might need to be put to a legal advisor?
Yes.
Commentary
Arbitrators often walk in fear of misconduct
applications, and many of the potential procedural advantages
of arbitration are lost when the legal representatives of the
parties make veiled or even overt threats to seek the removal
of the arbitrator for misconduct.
In this case, the application was roundly
dismissed, and of particular interest is the Court's comment
that the lawyers for the parties should be given more
assistance to a lay arbitrator.
Havant Borough Council v
South Coast Shipping Company Limited
Commercial Court His Honour Judge James
Fox-Andrews QC Judgment delivered 11th January 1996
Facts
The plaintiff engaged the defendant under an
ICE contract in connection with the Hayling Island Beach
Replenishment Scheme. The work was expected to be potentially
noisy, and the specification required contractors to minimise
disturbance to those living nearby.
South Coast Shipping's Method Statement
indicated that they "would work from 6.00am to 11.00pm during
the day"
Condition 29 of the Conditions of Contract
required South Coast Shipping to indemnify Havant against any
claims costs or expenses arising on account of noise or other
disturbance.
During the execution of the Works, a local
resident obtained an injunction restraining South Coast
Shipping subcontractors from making any noise audible from
the Plaintiff's house between the hours of 5.00pm and 9.00am.
South Coast Shipping sought a variation under
Clause 51 to cover the additional cost of the Works resulting
from the injunction. Various questions of law were determined
by the arbitrator, Mr Ian Menzies and in turn by the
Commercial Court by way of appeal.
Issues and findings
Was a method within the contractor’s Method
Statement within the definition of "Works" for the purposes of
Clause 13 and 14 of the ICE Contract?
Yes.
Was South Coast Shipping entitled to a
variation if the work was physically or legally
impossible?
Yes.
Was the Method Statement permissive or
mandatory?
Part permissive and part mandatory. The
question should be remitted to the Arbitrator.
Was it fatal to South Coast Shipping's Claim
D (trimming batters) that it had not been formally referred to
the Engineer for a decision?
Yes.
Commentary
This is a somewhat lengthy judgment running
to some 57 pages, and the interest in it is principally in the
detailed reasoning. But there are two somewhat generalised
and, to non-lawyers, perhaps somewhat surprising points which
it illustrates.
The first is that where a contractor is
required, pre contract, to satisfy the employer by identifying
the method that he proposes to adopt for the work, then the
employer may be required to bear the additional cost if that
method turns out to be unworkable. Many would say that such a
notion is nonsensical.
Secondly, a contractor who is aggrieved by a
refusal of an engineer to certify time or money may be barred
in a subsequent arbitration if he has not, pursuant to Clause
61, sought a "decision" from the Engineer upon the matter upon
which the engineer has already declined to budge. Bearing in
mind the considerable latitude that contractors are allowed in
the area of contractual notices, it seems strange that so much
importance should be attached to such an ostensibly redundant
procedural hoop.
Hoppe v Titman
Court of Appeal His Honour Judge Pill
LJ Judgment delivered 21st February 1996
Facts
Some years ago, Mr Titman sued Mr. & Mrs.
Hoppe for payment of his fees for architectural work.
The Hoppes pleaded a defence of set-off
alleging negligence, but there was no counter-claim. That
action was settled by acceptance of a payment into court.
Two years later, the Hoppes sued Mr. Titman
for professional negligence.
Issues and findings
Was the question of negligence res
judicata?
No.
Were the Hoppes free to pursue the allegation
of negligence?
Yes.
Commentary
Where a defendant is sued for non-payment for
building work (or indeed for any sort of goods and services)
and has not paid because of complaints about what was done,
the temptation is often to counterclaim. But where the
defendant does not wish to pursue a claim for a balance in his
favour, he is often better served by restricting his plea to
set-off, which operates as a shield but not a
counter-attacking sword. This is especially so where the
defendant is an overseas resident or limited company and thus
vulnerable to an application for security for costs (an order
for security for costs may be made against a counterclaiming
defendant, but not if the cross allegations are made only by
way of set-off).
This decision points up another reason why a
plea of set-off only may be preferable; it offers some
protection against the possibility that the plaintiff’s work
may be even more defective than originally feared.
B Mullan & Sons
(Contractors) Limited v Ross and Another
High Court of Northern Ireland, Chancery
Division Kerr J Judgment delivered 7 December 1995
Facts
The Plaintiff was a subcontractor to
McLaughlin & Harvey plc, who in turn were executing works
for the Londonderry Port and Harbour Commissioners when it
when into administrative receivership, as a result of which
its JCT 81 Contract was determined. Some three months later,
McLaughlin & Harvey was the subject of a resolution for
winding up and the Defendants were appointed liquidators.
Clause 27.4.3.1 of the Contract provided as
follows:-
Except where the determination
occurs by reason of the bankruptcy of the contractor
or of his having a winding up order made or (other
than for the purposes of amalgamation or reconstruction)
a resolution for voluntary winding up passed, the
contractor shall if so required by the employer
within 14 days of the date of determination, assign
to the employer without payment the benefit of any
agreement for the supply of materials or goods and/or
for the execution of any work for the purposes of
this contract but on the terms that a supplier or
subcontractor shall be entitled to make any reasonable
objection to any further assignment thereof by the
employer;
Clause 27.4.3.2 of the Contract
provided:-
Unless the exception to the
operation of Clause 27.4.3.1 applies the employer
may pay any supplier or subcontractor for any materials
or goods delivered or works executed for the purposes
of this contract (whether before or after the date
of determination) insofar as the price thereof has
not already been paid by the contractor.
The Liquidators argued that Clause 27.4.3.2
was void as being in conflict with Article 93 of the
Insolvency (Northern Ireland) Order 1989 which provides that a
Company's property in a voluntary winding up shall be applied
in satisfaction of the Company's liabilities pari passu.
It was common ground that Clause 27.4.3.1 did
not apply, since the main contract was determined by
McLaughlin & Harvey being placed in administrative
receivership.
Issues and findings
Was the Employer entitled to make direct
payment to the subcontractor?
No.
Commentary
The JCT altered their standard form contracts
as a result of the British Eagle decision in 1975 so as to
remove the provision for direct payments in cases where the
main contract is determined as a result of the main
contractor’s liquidation. Where there is a liquidation, the
insolvency scheme (ie, in broad terms, secured creditors get
paid first, then preferential creditors, then ordinary
unsecured creditors, and only then shareholders) applies in
priority to anything the contract may say. This case
illustrates that the same principle applies where the contract
is determined for a reason falling short of liquidation (eg.
administrative receivership) but where the Company
subsequently goes into liquidation.
John Barker Construction
Limited v London Portman Hotel Limited
Mr Recorder Roger Toulson QC, sitting as
Official Referee (Judgment delivered 16th April 1996)
Facts
The Plaintiff building contractors carried
out refurbishment works to the London Portman Hotel. Although
formal contract conditions were never executed, it was common
ground that they governed the contract, and that the JCT 80
Conditions applied, including the sectional completion
supplement. The standard arbitration clause was deleted and
replaced by the words:-
The proper law of the Agreement
shall be English and the English Court shall have
jurisdiction.
The works were delayed and the parties
entered into an acceleration agreement.
After the acceleration agreement, there were
further delays. The Defendant's Architect, Mr Miller, granted
certain extensions; the Plaintiffs claimed that they were
entitled to longer extensions of time, and to payment of
£20,000 arising out of the Acceleration Agreement.
Preliminary issues were ordered, inter alia,
as to the effect of the Acceleration Agreement, as to whether
the Court had jurisdiction to entertain the Plaintiff's claim
in relation to the extension of time granted by the Architect,
and, if and to the extent that the Court had such
jurisdiction, what was the proper determination of the
Plaintiff claim.
Issues and findings
What is the implied obligation on a
certifying Architect?
To act lawfully and fairly.
What are the powers of the Court if the
Architect fails to act lawfully and fairly?
The Court may declare the Architect's
decision invalid, but may not substitute its decision for that
of the Architect solely because it would have reached a
different decision.
What is the power of the Court if the
arbitration machinery breaks down?
The Court may substitute its own machinery to
ensure enforcement of the parties' substantive rights and
obligations that a fair and reasonable extension should be
given.
Where the certification is challenged, will
the Court embark upon a detailed examination of the way in
which the Architect made his certificates?
The Court made such an examination in this
case.
What was the effect of the Architect making
an impressionistic assessment, instead of a logical analysis,
of the delay?
It rendered his extension of time
fundamentally flawed. The contractual machinery had broken
down to such an extent that the Court would substitute its own
assessment.
Was the Plaintiff entitled to the £20,000
under the Acceleration Agreement?
It was impossible to tell whether, but for
changes made by the employer, the Plaintiffs would have
achieved the bonus. The Plaintiffs were entitled to 50% by way
of loss of a chance.
Commentary
The approach of the Court in this case differs somewhat
from the approach of the Court of Appeal in Balfour
Beatty v Docklands Light Railway in two important
respects, albeit that the end result is much the same.
First, the Court did not in this case pick up
the implied term from the Balfour Beatty case, that
certificates must not merely be "honest" and "fair" but also
"reasonable". Although this judgment was delivered after the
Balfour Beatty judgment, it was argued some months earlier,
and Mr Recorder Toulson was apparently unaware of the Balfour
Beatty decision.
Secondly, Mr Recorder Toulson took a
different line as to the effect of a failure of the certifier
to meet the certified standard. In the Balfour Beatty case,
the Court of Appeal said that the courts do not have power to
review certificates, and said that the remedy of an aggrieved
contractor is to sue for damages for breach of contract. In
this case, Mr Recorder Toulson latched on to the exception to
the Crouch Rule referred to in Crouch itself, namely that the
Court does have power to review certificates where the
contractual machinery has "broken down". But reading the full
judgment in this case suggests that the certification process
ran along fairly typical lines; Mr Recorder Toulson described
the failure of the architect to perform a proper retrospective
delay analysis as a fundamental flaw, and yet in practice, it
is the exception rather than the rule for architects to make
such an analysis.
Another point of apparent criticism of the
architect was his acknowledgement that it was "unfortunate"
that he had discussed his proposed award with the employer,
giving the employer the opportunity of comment, without
offering a comparable opportunity to the contractor. Again,
such behaviour on the part of architects is typical.
By way of evidence, the contractors came to court armed
with a detailed delay analysis, but the employers did
not. The court adopted the line of McAlpine v McDermott
that such an analysis was necessary, and adopted the
contractor's analysis subject only to some minor points.
This pointed out a procedural issue; that the Court
does not ordinarily have the means to perform the very
complex computer-aided calculations that are needed
in retrospective delay analysis, and we understand that
the contractor's expert, Keith Pickavance, was effectively
asked to go away and run the adjustments indicated by
the court through his computer program.
An interesting end note to the case concerned
the reference to loss of a chance. It has long been the law
that if the Defendant is guilty of a breach of contract, but
the Plaintiff cannot prove that he would necessarily have
achieved any benefit but for the breach, yet the Plaintiff may
recover damages for loss of a chance. The doctrine is
sometimes invoked in claims against professionals or managers
who fail to take proper protective measures on behalf of their
clients, but then argue the absence of any direct proof that
such measures would have been successful. This case represents
a somewhat rare example of the doctrine being applied in a
judgment.
Since delivering this judgment, Mr Toulson
has been appointed to the High Court Bench.
Abbey National Mortgages
PLC and Others v Key Surveyors Nationwide Limited
and Others
Court of Appeal Sir Thomas Bingham MR,
Peter Gibson and Schiemann LLJ (Judgment delivered 5th
February 1996)
Facts
The Plaintiff was in the business of
providing mortgage finance; the First Defendant was a company
providing professional valuations of properties, a company now
insolvent and which has ceased trading. The Second to Ninth
Defendants were individual Surveyors who had made valuations
on which the Lenders had relied.
The action concerned allegedly negligent
valuations of 29 properties in various parts of the country.
The Defendants sought leave for 29 expert
witnesses, one for each property, on the basis that local
experience would be necessary in each case. At first instance,
the Official Referee, His Honour Judge Hicks QC, made an order
appointing just one Court expert, with the parties being
limited to one expert each upon the Court Expert's report.
The Defendants appealed.
ORDER 40, Rule 1 provides:-
(1) In any cause or matter which is to be
tried without a jury and in which any question for an expert
witness arises the Court may at any time, on the application
of any party, appoint an independent expert or, if more than
one such question arises, two or more such experts, to inquire
and report upon any question of fact or opinion not involving
questions of law or of construction.
An expert appointed under this paragraph is
referred to in this Order as a "court expert".
(2) Any court expert in a cause or matter
shall, if possible, be a person agreed between the parties
and, failing agreement, shall be nominated by the Court.
(3) The question to be submitted to the court
expert and the instructions (if any) given to him shall,
failing agreement between the parties, be settled by the
Court.
(4) In this rule "expert", in relation to any
question arising in a cause or matter, means any person who
has such knowledge or experience of or in connection with that
question that his opinion on it would be admissible in
evidence."
ORDER 40, Rule 4 provides:-
"Any party may, within 14 days after
receiving a copy of the Court expert's report, apply to the
Court for leave to cross-examine the expert on his report, and
on that application the Court shall make an order for the
cross-examination of the expert by all the parties either -
(a) at the trial, or (b) before an examiner at such time and
place as may be specified in the order".
Order 40, Rule 6 provides:-
"Where a court expert is appointed in a cause
or matter, any party may, on giving to the other parties a
reasonable time before the trial notice of his intention to do
so, call one expert witness to give evidence on the question
reported on by the court expert but no party may call more
than one such witness without the leave of the Court, and the
Court shall not grant leave unless it considers the
circumstances of the case to be exceptional."
Issues and findings
Was the novelty of the Order made
objectionable?
No. Exhortations to trial judges to be
interventionist and managerial would be futile if every
managerial initiative of a trial judge were to be condemned as
an unwarranted departure from orthodoxy.
Is Order 40 limited to questions of a
scientific or technical kind?
No.
Is it only appropriate to appoint a court
expert under Order 40 to give an opinion on a subsidiary
question, and not on the major issue on which the Court had to
resolve?
No.
Is a person prevented from being a court
expert if he lacks personal knowledge of the matters upon
matters which he must report?
No.
Where a court expert is ordered to inquire
and report on more than one question, are the parties entitled
to call one witness per question?
No.
Is a court expert strictly bound by the rules
of evidence?
No.
Is the appointment of a court expert
pointless, as the mere introduction of an additional expert
whose opinion would carry no more weight than any other?
No; the experience of the Court is that
expert witnesses appointed by the parties do tend to become
partisan. There must be a reasonable chance that an expert
appointed by the Court, with no axe to grind, may prove a
reliable source of expert opinion.
Should the Judge's order in this case be
disturbed?
No. The orders were not necessarily final. In
considering any further application, the Judge would bear in
mind not only that professional reputations were at stake, but
also the balance between costs of the litigation and the sums
at stake.
Bowmer and Kirkland
Limited v Wilson Bowden Properties Limited
His Honour Judge Hicks QC, Official
Referee (Order made 14th July 1995. Reasons dated 27th July
1995. Released for publication 16th April 1996)
Facts
The plaintiff contractor sued the defendant
employer in respect of £71,250 retention money, and by
amendment, £83,871 for work done. The defendant
counter-claimed for £834,298 and general damages for defective
work.
The Plaintiff made a payment into court in
respect of the net value of the counter-claim, and also, on
the same day made a Calderbank offer dealing with the
retention money which had been paid into a separate bank
account.
The Defendant applied for interim payment
under Order 29 in respect of its counter-claim.
Issues and findings
Is a party entitled to refer to a payment
into Court on interim payment application?
Yes (following the Court of Appeal’s decision in
Fryer v. London Transport Executive (1987), The
Times 4 December 1987 and not following A Limited
v. B Limited (1991) 29 Con LR 53).
Was a Calderbank offered to be treated as on
the same footing as a payment in?
It was so treated in this case, but the court
expressly left open that question.
What weight should be given to a payment in
on an interim payment application?
The appropriate weight depends on the
circumstances. A payment in representing a "nuisance value"
carries minimal weight, if any. Again, a payment in may
reflect the odds of success or failure rather than any
expected outcome.
Should an order for interim payment be made
in this case?
Yes.
Commentary
It is a long established feature of payments
into court that they may not be made known to the judge until
the judge has decided the case, and comes to consider the
question of costs.
It therefore came as something of a surprise
in 1987 when the Court of Appeal found in the personal
injuries case of Fryer -v- London Transport Executive that, if
a payment into court is made, the other party may refer the
court to it on an application for interim payment under Order
29.
In A Limited v. B Limited in 1991 (CILL April
1992) His Honour Judge John Davies QC declined to follow
the Fryer decision. CILL predicted then that it was
by no means a foregone conclusion that every court would
be able to follow Judge Davies’ robust attitude, and
so it has proved.
Proposed Legislation and Reports
Housing Grants Construction
And Regeneration Bill
The proposed legislation pursuant to Sir
Michael Latham's proposals, outlined in the Queen's speech
(CILL page 1114), was introduced into the House of Lords at
the beginning of February as Part II of the Housing Grants,
Construction and Regeneration Bill. The Bill is now due to
become law by about the end of July.
The proposed legislation will apply to all
construction contracts except those signed by Householders.
Attempts in the House of Lords to limit its applicability have
not been successful.
As set out in the Explanatory Memorandum to
the Bill, it will give any party to a constructions contract a
right to refer disputes to a quick, impartial and
investigative adjudication procedure. If no adequate procedure
is agreed in the contract, one set out by the Government in
secondary legislation will apply. Contractors will have a
statutory right to insist on payment by instalments where the
work is to last 60 days or more. A payer will have to give the
Contractor notice, with reasons, if he wishes to set off
against the payments due. Pay when paid clauses are to become
unenforceable, save in the case of actual ultimate payer
insolvency.
EXTRACTS FROM THE BILL
Clause 103 - (1) In this Part a "construction contract"
means an agreement for the carrying out of construction
operations.
- This part applies only to construction contracts
which…are entered into after the commencement of this Part
...
- Clause 105 - (1) This Part does not apply to a
construction contract if one of the parties to the contract
occupies, or intends to occupy, as his residence a dwelling
the whole or any part of which is the subject of operations
to which the contract relates.
Clause 106 -(1) The provisions of this Part
apply only where the construction contract is in writing, and
any other agreement between the parties as to any matter is
effective for the purposes of this Part only if in writing.
The expressions "agreement", "agree" and "agreed" shall be
construed accordingly.
- There is an agreement in writing -
- if the agreement is made in writing (whether or not it
is signed by the parties),
- if the agreement is made by exchange of communications
in writing, or
- if the agreement is evidenced in writing.
- Where parties agree otherwise than in writing by
reference to terms which are in writing, they make an
agreement in writing.
- An agreement is evidenced in writing if an agreement
made otherwise than in writing is recorded by one of the
parties, or by a third party, with the authority of the
parties to the agreement.
- An exchange of written submissions in arbitral or legal
proceedings in which the existence of an agreement otherwise
than in writing is alleged by one party against another
party and not denied by the other party in his response
constitutes as between those parties an agreement in writing
to the effect alleged.
- References in this Part to anything being written or in
writing include its being recorded by any means.
Adjudication
Clause 107 - (1) A party to a construction
contract has the right to refer a dispute arising under the
contract for resolution by an adjudication procedure complying
with this section.
For this purpose "dispute" includes any
difference.
- The procedure must -
- provide a timetable with the object of securing -
(i )the appointment of the adjudicator and referral of
the dispute to him within 7 days, and
(ii) a decision within 14 days of referral;
- require the adjudicator to reach a decision in any
event within 28 days of referral;
- impose a duty on the adjudicator to act impartially;
and
- enable the adjudicator to take the initiative in
ascertaining the facts and the law.
If the contract does not provide for such a
procedure, the relevant provisions of the Scheme for
Construction Contracts apply.
Payment
Clause 108 - (1) A party to a construction
contract is entitled to payment by instalments, stage Payments
or other periodic payments for any work under the contract
unless-
- it is specified in the contract that the duration of the
work is to be less than 60 days, or
- it is agreed between the parties that the duration of
the work is estimated to be less than 60 days.
- The parties are free to agree the amounts of the stage
payments and the intervals at which, or circumstances in
which, they become due.
- In the absence of such agreement, the relevant
provisions of the Scheme for Construction Contracts apply.
Clause 109 - (1) Every construction contract
shall -
- provide an adequate mechanism for determining what
payments become due under the contract, and when, and
- provide for a final date for payment in relation to any
sum which becomes due.
The parties are free to agree
how long the period is to be between the date on which a sum
becomes due and the final date for payment.
- If or to the extent that a contract does not contain
such provision, the relevant provisions of the Scheme for
Construction contracts apply.
Clause 110 - (1) A party to a construction
contract may not withhold payment after the final date for
payment of a sum due under the contract unless he has given an
effective notice of intention to withhold payment.
- To be effective such a notice must specify
- the amount proposed to be withheld and the ground for
withholding payment, or
- if there is more than one ground, each ground and the
amount attributable to it,
and must be given not later than the
prescribed period before the final date for payment.
- the parties are free to agree what that prescribed
period is to be,
In the absence of such agreement, the period
shall be that provided by the Scheme for Construction
Contracts.
- Where an effective notice of intention to withhold
payment is given, but on the matter being referred to
adjudication it is decided that the whole or part of the
amount should be paid, the award shall be construed as
requiring payment not later than-
- seven days from the date of the award, or
- the date which apart from the notice would have been the
final date for payment,
whichever is the later.
Clause 111 -
- Where a sum due under a construction contract is not
paid in full by the final date for payment and no effective
notice to withhold payment has been given, the person to
whom the sum is due has the right (without prejudice to any
other right or remedy) to suspend performance of his
obligations under the contract to the Party by whom payment
ought to have been made ("the party in default").
- The right may not be exercised without first giving to
the party in default at least seven days' notice of
intention to suspend performance, stating the ground or
grounds on which it is intended to suspend performance.
- the right to suspend performance ceases when the party
in default makes payment in full of the amount due.
- Any period during which performance is suspended in
pursuance of the right conferred by this section shall be
disregarded in computing any contractual time limit for the
completion, by the party exercising the right or by a third
party, of any work directly or indirectly affected by the
exercise of the right. Where the contractual time limit is
set by reference to a date rather than a period, the date
shall be adjusted accordingly.
Clause 112 -
(1) A provision
purporting to make payment under a construction contract
conditional on the payer receiving payment from a third
person is void, unless that third person, or any other
person payment by whom is under the contract (directly or
indirectly) a condition of payment by that third person, is
insolvent.
(2) For the purposes of
this section a company becomes insolvent -
- on the making of an administration order against it
under Part II of the Insolvency Act 1986,
- on the appointment of an administrative receiver or a
receiver and manager of its property under Part III of
that Act,
- on the passing of a resolution for voluntary
winding-up without a declaration of solvency under section
89 of that Act, or
- on the making of a winding-up order under Part IV or V
of that Act.
(3) For the purposes of this section a
partnership becomes insolvent -
- on the making of a winding-up order against it under
any provision of the Insolvency Act 1986 as applied by an
order under section 420 of that Act, or
- when sequestration is awarded on the estate of the
partnership under section 12 of the Bankruptcy (Scotland)
Act 1985 or the partnership grants a trust deed for its
creditors.
(4) For the purposes of this section an
individual becomes insolvent -
- on the making of a bankruptcy order against him under
Part IX of the Insolvency Act 1986, or
- on the sequestration of his estate under the
Bankruptcy (Scotland) Act 1985 or when he a trust deed for
his creditors.
(5) A company, partnership or individual
shall also be treated as insolvent on the occurrence of any
event corresponding to those specified in subsection (2),
(3) or (4) under the law of Northern Ireland or of a country
outside the United Kingdom.
(6) Where a provision is rendered void
by subsection (1), the parties are free to agree other terms
for payment. In the absence of such agreement, the
relevant provisions of the Scheme for Construction Contracts
apply.
Supplementary provisions
Clause 113 - (1) The Minister shall by
regulations make a scheme ("the Scheme for Construction
Contracts") containing provision about the matters referred to
in the preceding provisions of this Part.
- Before making any regulations under this section the
Minister shall consult such persons as he thinks fit.
- In this section "the Minister" means -
- for England and Wales, the Secretary of State, and
- for Scotland, the Lord Advocate.
Clause 114 - (1) The parties are free to
agree on the manner of service of any notice or other document
required or authorised to be served in pursuance of the
construction contract or for any of the purposes of this
Part.
(2) If or to the extent that there is no such agreement
the following provisions apply.
(3) A notice or other document may be served on a person
by any effective means.
(4) If a notice or other document is addressed, pre-paid
and delivered by post -
- to the addressee's last known principal residence or,
if he is or has been carrying on a trade, profession or
business his last known principal business address, or
- where the addressee is a body corporate, to the body's
registered or principal office,
it shall be treated as effectively
served.
(5) this section does not apply to the service of
documents for the purposes of legal proceedings, for which
provision is made by rules of court.
(6) References in this Part to a notice or other document
include any form of communication in writing and references
to service shall be construed accordingly.
Clause 115 - (1) For the purposes of this
Part periods of time shall be reckoned as follows.
(2) Where an act is required to be done within a
specified period after or from a specified date, the period
begins immediately after that date.
(3) Where the period would include Christmas Day, Good
Friday or a day which under the Banking and Financial
Dealings Act 1971 is a bank holiday in England and Wales or,
as the case may be, in Scotland, that day shall be
excluded.
Architects
Clause 116 - (1) The Architects' Registration
Council of the united Kingdom established under the Architects
(Registration) Act 1931 ("the 1931 Act") shall be known as the
Architects Registration Board.
(2) The Board of Architectural Education, the Admission
Committee and the Discipline Committee constituted under the
1931 Act are abolished.
(3) In section 3 of the 1931 Act (constitution and
functions of Architects' Registration Council), after
subsection (2) insert -
"(2A) Part I of the First Schedule to this
Act makes provision about the constitution and proceedings
of the Board.
(2B) There shall be a Professional Conduct
Committee of the board and Part II of that Schedule makes
provision about its constitution and proceedings.
(2C) Part III of that Schedule gives to the
Board power to establish other committees and makes
provision about their constitution and proceedings.
(2D) Part IV of that Schedule makes
"general provision about the Board and its
committees.".
(4) For the First Schedule to the 1931 Act (constitution
of Council) substitute the Schedule set out in Part I of
Schedule 2.
Clause 115 for section 4 of the 1931 Act
substitute -
"The Registrar.
- (1)The Board shall appoint a person to be known as the
Registrar of Architects.
(2) the Board shall determine the period for which, and
the terms on which, the Registrar is appointed.
(3) The Registrar shall have the functions provided by or
by virtue of this Act and any other functions provided by or
by virtue of this Act and any other functions which the
board directs.
(4) The Board may, in addition to paying to the Registrar
a salary or fees-
- pay pensions to or in respect of him or make
contributions to the payment of such pensions; and
- pay him allowances, expenses and gratuities.
Staff.
4A. (1) The Board may appoint staff.
(2) The Board shall determine the period for which, and
the terms on which, its staff are appointed.
(3) Staff appointed by the Board shall have the duties
which the Board directs.
(4) the Board may, in addition to paying salaries to its
staff -
- pay pensions to or in respect of them or make
contribution to the payment of such pensions; and
- pay them allowances, expenses and gratuities."
Right To Conduct
Litigation
Advice of the Lord Chancellor's Advisory
Committee on Legal Education and Conduct to the Institute of
Commercial Litigators.
(Advice dated 2nd February 1996)
BACKGROUND
Historically, the right to conduct litigation
in the courts has been the exclusive province of solicitors;
conversely, there has been no restriction on the right of
unqualified Claims Consultants or others to conduct
arbitration proceedings on behalf of clients.
The Courts and Legal Services Act 1990
contains machinery whereby the Lord Chancellor may authorise
other bodies to have the right to conduct litigation, and to
have rights of audience before courts, where that is in
pursuance of the "statutory objective", namely making
provision for new or better ways of providing advocacy in
litigation services and a wider choice of persons providing
them, while maintaining the proper and efficient
administration of justice.
For the purpose of deciding whether to
authorise any other body, the Lord Chancellor is advised by an
Advisory Committee of 17 people, 8 of whom are lawyers and 9
of whom are not.
Under Section 70 of the Courts and Legal
Services Act 1990, it is an offence punishable by imprisonment
for a term of up to 2 years and/or a fine for any person to do
any act in the purported exercise of a right to conduct
litigation in relation to any proceedings when he is not
entitled to exercise that right.
In December 1993, the Institute of Commercial
Litigators made an application to the Advisory Committee,
seeking authorisation to grant to its Fellows rights to
conduct litigation in building, construction and engineering
matters in Court, together with certain limited rights of
audience in interlocutory proceedings arising out of such
litigation.
By a majority of 15 to 4, the Committee's
advice, in the first instance offered to the Institute of
Commercial Litigators itself, was that the application fell
far short of what was required.
EXTRACTS FROM THE ADVICE
The Advisory Committee's conclusion
"In the light of the evidence the Committee
concludes that the current application falls far short of what
is required by the statutory objective and the general
principle. The Committee believes that for the Institute, as
currently constituted, to be permitted to grant the proposed
rights could extend choice only at the serious risk of
substantially lowering standards of service to the public.
Such a result would not be consistent with the proper and
efficient administration of justice. The committee also takes
the view that the Institute of Commercial Litigators, as
currently constituted, is not a body capable of enforcing
qualification regulations or rules of conduct as required by
the general principle.
The present advice is concerned only with the
current application, and it is not for the Committee to
prejudge any future application that the Institute may wish to
make. In relation to any proposed application for
authorisation to grant rights of audience or litigation,
paragraph 1(5) of schedule 4 to the Act requires the Committee
to advise the applicant "of the extent to which (if at all)
the draft regulations or rules should ... be amended in order
to make them better designed (a) to further the statutory
objective; or (b) to comply with the general principle". Some
of the fundamental defects of the application relate to the
reality (or lack of it) of the Institute of Commercial
Litigators as currently constituted. The Committee believes
that these defects in the application, which is the only
matter now under consideration, cannot be remedied by any
amendments to the proposed rights or any reformulation of the
proposed rules of conduct or qualification regulations.
Quality
The Committee believes that the statutory
objective of promoting new or better ways of supplying
litigation or advocacy services does not include ways that
would lead to a substantial lowering of standards. For the
protection of the public, the proper and efficient
administration of justice requires that those granted rights
of litigation or audience should be competent to exercise
them. On the evidence submitted by the applicant and others,
the Committee believes the scheme outlined in the current
application to be incapable of bringing the majority of
Fellows of the Institute to a level of competence appropriate
to the exercise by them of the rights sought.
The Institute claims that "the client's
consultant, through his understanding of the technical
background and familiarity with the industry, is likely to
have greater ability to interpret the relevant legal issues".
The Committee has received evidence that this claim
underestimates the skills required for the proper exercise of
the rights that the Institute seeks authority to grant. In
disputes arising from construction matters, as in other
litigation involving significant legal and procedural
difficulty and complexity, litigation and advocacy skills are
not mere appendages to technical expertise in engineering or
other aspects of construction work. They are skills which
themselves take years of training and experience to develop.
The Committee is not satisfied that the Institute's proposals
for education and training would provide a threshold level of
competence for the generality of Fellows.
Rights of audience
The proposed rights of audience would be
confined to interlocutory matters. However, such matters range
extremely widely from relatively simple to highly complex
matters. In some cases, the legal issues raised in an
interlocutory application are just as complex as any that may
arise at a final hearing. Moreover, in many cases is cannot be
known in advance what degree of legal and advocacy skills will
be required at any particular hearing including, for example,
a hearing which may start out as an apparently simple summons
for directions.
The Committee considers that many complex
legal matters arising in interlocutory applications will be
beyond the competence of the generality of Fellows of the
Institute. The Committee does not accept that they will be in
the same position in this regard as those in practice as
barristers or solicitors, who will have broader legal
knowledge and experience.
Rights to conduct litigation
The Committee has taken into account that
some members of the Institute have experience in the conduct
of arbitrations. Having carefully considered that factor, the
Committee believes that it cannot outweigh the serious defects
of the application.
Breadth of legal knowledge and experience
This advice has already adverted to the fact
that the legal knowledge and experience of the generality of
Fellows of the Institute will not be as broad as those
practising as solicitors or barristers. In consequence a
Fellow would be in a weak position to deal with the legal
issues of various different sorts that may arise unexpectedly
in connection with a construction dispute even assuming that
he had the right to do so. Annex D sets out the committee's
advice relating to education and training.
Cost
The Committee does not accept that any case
has been made out that litigation or advocacy services
provided by Fellows of the Institute would be cheaper than
those provided by solicitors and barristers. Even if Fellows
were to charge lower hourly rates, their relative lack of
knowledge and experience in dealing with the work might result
in inefficiency and higher cost for the client.
Conflicts
The committee is satisfied that the potential
for conflicts created by the application is greater than that
normally facing solicitors, because of the wider range of
activities undertaken by claims consultants in the
construction field. For example, at present one of the prime
functions of claims consultants is to provide expert evidence
in construction litigation. As in other fields it is vital
that such evidence be independent and objective. The Committee
believes that there could well be unacceptable pressure on an
expert witness who is employed by a firm of claims consultants
and commercial litigators, which is also conducting the
litigation to which his evidence relates. Such pressure is
also likely to militate powerfully against the maintenance of
proper standards in relation to the discovery of documents.
The Conclusion of the dissenting Members of
the Committee was as follows:
We would agree that the application by the
Institute of Commercial Litigators requires considerable
further development, especially in relation to its education
and training proposals, before it is likely to satisfy the
requirements of the Act. Nor would we claim to have covered
all possible areas where further amendments are required. In
particular, we suspect that more consideration is needed of
the Institute's proposals for professional indemnity
cover.
We see it as the primary duty of the
Committee to assist applicants in preparing and developing
their proposals prior to their formal submission to the Lord
Chancellor for approval, and it is obvious from much of what
we have said so far that we do not consider that the majority
of the committee has adequately performed this role in
relation to the application by the Institute of Commercial
Litigators. In putting forward this dissent we hope to have
gone some way to remedy this situation and in that way to act
within both the letter and spirit of the courts and Legal
Services Act 1990."
Commentary
The emphatic rejection by the Advisory
Committee of the Institute of Commercial Litigators'
application will be welcome to some, less so to others. On the
one hand James R Knowles have invested significant sums in
pursuing this application and will no doubt be bitterly
disappointed by the result. As against that, Solicitors who
have opposed the application are always sensitive to the
charge that they may be selfishly protecting a monopoly, and
will take comfort from the fact that the majority of the
Committee including it seems the majority of the lay members,
have condemned the application in such round terms.
The main sponsors of the Institute of
Commercial Litigators, James R Knowles Limited, have had
considerable success in a number of advisory fields over the
years; this application appears however, to have been a bridge
too far for them.
Chambers & Partners'
Directory 1995-96 Construction and Civil Engineering London
Rankings
First Rank
Fenwick Elliott
Masons
Second Rank
Freedman Church
Third Rank
Baker & McKenzie
Bristows Cooke & Carpmael
Davies Arnold Cooper
McKenna & Co.
Rowe & Maw
Winward Fearon
Fourth Rank
Allen & Overy
Clifford Chance
Dibb Lupton Broomhead
Freshfields
Linklaters & Paines
Lovell White Durrant
McGrigor Donald
Nabarro Nathanson
Fifth Rank
Alsop Wilkinson
Ashurst Morris Crisp
S J Berwin & Co.
Berwin Leighton
Brecher & Co.
Denton Hall
D J Freeman
Eversheds
Forsyte Saunders Kerman
Fox & Gibbons
Glovers
Gouldens
Hextall, Erskine
Lane & Partners
Norton Rose
Park Nelson Thompson Quarrell
Rosling King
Simmons & Simmons
Speechly Bircham
Stephenson Harwood
Trowers & Hamlins
Wedlake Bell
Sixth Rank
Field Fisher Waterhouse
Vizards
Warner Cranston
Professional indemnity and regional firms are
listed separately
Index
ADJUDICATION
Proposed new statutory right to adjudication;
Housing
Grants, Construction and Regeneration Bill
ARBITRATION
Effectiveness of "pre-consent" to appeal from
arbitrator;
Vascroft
v Seeboard
Duty of Parties Lawyers to assist Lay
Arbitrator; Colt
International v Tarmac Construction
ARCHITECTS
Proposed reform of ARCUK; Housing
Grants, Construction and Regeneration Bill
Failure of Certifying Architect to make retrospective
delay analysis; John
Barker Construction Limited v London Portman Hotel
Limited
CERTIFICATES
No general power of the Courts to open up
Certificates, but Certifying Employer to act honestly,
fairly and reasonably; Balfour
Beatty v Docklands Light Railway Limited
True Interpretation of the Crouch
Decision; Contractual Machinery Broken Down; John
Barker Construction Limited v London Portman Hotel
Limited
CLAIMS
No extra-contractual recovery route where express
agreement; Clarksteel
Limited v Birse Construction Limited
COMMISSIONING
The purpose of commissioning; AEG
(UK) Limited v Translift Monorail Limited
CONTRACT
No party may take advantage of his own wrong; Vascroft
v Seeboard
CONTRIBUTION
Civil Liability (contribution) Act 1978; Birse
v Haiste
Recalculation of damages that would have been
recovered by a claimant but for settlement; Bristol
& West Building Society v Christie and
Others
DAMAGES
No reduction of damages for insurance recovery; Bristol
& West Building Society v Christie and
Others
Damages for Loss of a Chance; John
Barker Construction Limited v London Portman Hotel
Limited
DOM/2
Failure of subcontractor to give notice of practical
completion; Vascroft
v Seeboard
EXPERTS
Effect of British Standard not expert issue; Clarksteel
Limited v Birse Construction Limited
Appointment of Court Expert; Scope of Order
40; Role of Court Appointed Expert; Abbey
National Mortgages v Key Surveyors
HEALTH AND SAFETY
Relevance of Safety Settings; AEG
(UK) Limited v Translift Monorail Limited
HUDSON FORMULA
General review; Alfred
McAlpine Homes v Property and Land Contractors
ICE CONDITIONS OF CONTRACT
Construction of Method Statement; Method part of
"the Works"; Entitlement to Variation order in case
of Physical or legal Impossibility; Claim barred if
not referred to Engineer prior to Arbitration; Havant
Borough Council v South Coast Shipping Company
Limited
INSOLVENCY
JCT Provisions for Direct Payment of
subcontractors; Insolvency (Northern Ireland) Order
1989; B
Mullan & Sons (Contractors) Limited v Ross and
Another
INTERIM PAYMENT
Referring Court to Payment in; Relevance of
Payment in; Bowmer
and Kirkland Limited v Wilson Bowden Properties
Limited
LOSS AND EXPENSE
Recovery of overheads and rates for plant; Alfred
McAlpine Homes v Property and Land Contractors
PAYMENT INTO COURT
Res Judicata; Hoppe
v Titman
PAY-WHEN-PAID
Proposed unenforceability of pay-when-paid
Clauses; Housing
Grants, Construction and Regeneration Bill
PRACTICE
Binding nature of Court of Appeal decisions; Bowmer
and Kirkland Limited v Wilson Bowden Properties
Limited
PROCEDURE
Approach to Novel Orders; Abbey
National Mortgages v Key Surveyors
The Right to Conduct Litigation; Lord
Chancellor's Advisory Committee Report
SALE OF GOODS
Fitness for Purpose; AEG
(UK) Limited v Translift Monorail Limited
SET-OFF
Proposed statutory restriction on right of
set-off;
Housing
Grants, Construction and Regeneration Bill
|
|